Gold Mountain Provides Construction Update

VANCOUVER, BC / ACCESSWIRE / June 10, 2021 / Gold Mountain Mining Corp.

With the Company receiving its early works permit and waste rock mining already underway through our gravel borrow, operations will be in full stride once we receive our mining permit amendment.

The Company selected an area near PIt 2 for the gravel borrow in order to execute on a strategy that allows Gold Mountain to adhere to its aggressive timelines and accelerate the path to hit its high-grade 1300 vein.

Additionally, on May 7, 2021, the Company received a letter of authorization from the Ministry of Environment and Climate Change Strategy related to dewatering of the historical open pits under the existing Effluent Discharge Permit.

Nhwelmen-Lake has mobilized various pieces of equipment to the Elk Gold Mine to support site construction activities, including; tracked dozers, excavators, a production blast-hole drill, rock trucks and a mobile jaw crusher.

Once the final Mine Permit is issued, the Company anticipates beginning it’s large scale waste rock mining operations through July and August.

Prior to delivery to New Gold’s New Afton Mine, the ore will be assayed by an independent third party and weighed on site to determine the ore’s value.

Forward- looking statements include statements that are based on assumptions as of the date of this news release and are not purely historical including any information or statements regarding beliefs, plans, expectations or intentions regarding the future and often, but not always, use words or phrases such as “expects” or “does not expect”, “is expected”, “anticipates” or “does not anticipate”, “plans”, “estimates” or “intends”, or stating that certain actions, events or results “may”, “could”, “would”, “might” or “will” be taken, occur or be achieved.

…Read the full story